21-031 Harbor Street Bistro: Pergola
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Layout | 2 | |
| Assembly | 58 | |
| Finish | 13 | |
| Paint | 7 | |
| Travel | 29 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 883.00 | Bar stock | Tri-State Fasteners | |
| 592.00 | Hardware | Summit Powder Coat | |
| 310.00 | Plate | Keystone Metals Supply | |
| $1785.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Layout | 2 | 105 | 13.5 | 708.75 |
| Assembly | 58 | 3045 | 11 | 577.5 |
| Finish | 13 | 682.5 | 28.1 | 1475.25 |
| Paint | 7 | 367.5 | 35 | 1837.5 |
| Travel | 29 | 1522.5 | 25 | 1312.5 |
| Total | 109 | $8175.00 | 112.6 | $8445.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 370.00 | Bar stock | Keystone Metals Supply | |
| 1771.00 | Plate | Allied Welding Gas | |
| $2141.00 | Total | All Sources | |