21-030 Delacroix Residence: Handrail
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Measure & Fit | 8 | |
| Assembly | 19 | |
| Finish | 22 | |
| Install | 19 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1706.00 | Plate | Allied Welding Gas | |
| 1310.00 | Powder coat | Keystone Metals Supply | |
| 672.00 | Hardware | Keystone Metals Supply | |
| $3688.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Measure & Fit | 8 | 420 | 7.5 | 393.75 |
| Assembly | 19 | 997.5 | 2 | 105 |
| Finish | 22 | 1155 | 16 | 840 |
| Install | 19 | 997.5 | 11.8 | 619.5 |
| Total | 68 | $5100.00 | 37.3 | $2797.50 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1293.00 | Hardware | Allied Welding Gas | |
| 2330.00 | Bar stock | Allied Welding Gas | |
| 2108.00 | Tube | Tri-State Fasteners | |
| $5731.00 | Total | All Sources | |