21-025 Copperleaf Winery: Fence
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 14 | |
| Measure & Fit | 7 | |
| Assembly | 45 | |
| Finish | 6 | |
| Paint | 18 | |
| Travel | 13 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 641.00 | Bar stock | Summit Powder Coat | |
| 1685.00 | Hardware | Allied Welding Gas | |
| $2326.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 14 | 735 | 24.5 | 1286.25 |
| Measure & Fit | 7 | 367.5 | 7.9 | 414.75 |
| Assembly | 45 | 2362.5 | 18 | 945 |
| Finish | 6 | 315 | 3.5 | 183.75 |
| Paint | 18 | 945 | 14 | 735 |
| Travel | 13 | 682.5 | 11 | 577.5 |
| Total | 103 | $7725.00 | 78.9 | $5917.50 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 996.00 | Powder coat | Allied Welding Gas | |
| 551.00 | Hardware | Keystone Metals Supply | |
| $1547.00 | Total | All Sources | |