21-023 Old Mill Lofts: Balcony Railing
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 8 | |
| Measure & Fit | 12 | |
| Layout | 12 | |
| Assembly | 45 | |
| Finish | 17 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 751.00 | Plate | Summit Powder Coat | |
| 672.00 | Tube | Allied Welding Gas | |
| $1423.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 8 | 420 | 0 | |
| Measure & Fit | 12 | 630 | 11 | 577.5 |
| Layout | 12 | 630 | 0 | |
| Assembly | 45 | 2362.5 | 0 | |
| Finish | 17 | 892.5 | 1.5 | 78.75 |
| Total | 94 | $7050.00 | 12.5 | $937.50 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 216.00 | Hardware | Allied Welding Gas | |
| 1677.00 | Plate | Allied Welding Gas | |
| $1893.00 | Total | All Sources | |