21-023 Old Mill Lofts: Balcony Railing

Customer Contact Information

Project Details

Structure

Estimate

Labor Estimate

Type Hours
Handling 8
Measure & Fit 12
Layout 12
Assembly 45
Finish 17

Estimated Cost Sources

Cost Description Vendor
751.00 Plate Summit Powder Coat
672.00 Tube Allied Welding Gas
$1423.00 Total All Sources

REPORT

Labor Summary

Type Estimated Hours Estimated Cost Actual Hours Actual Cost
Handling 8 420 0
Measure & Fit 12 630 11 577.5
Layout 12 630 0
Assembly 45 2362.5 0
Finish 17 892.5 1.5 78.75
Total 94 $7050.00 12.5 $937.50

Costing and Invoices

Cost Description Vendor
216.00 Hardware Allied Welding Gas
1677.00 Plate Allied Welding Gas
$1893.00 Total All Sources