21-019 Old Mill Lofts: Canopy
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 13 | |
| Layout | 13 | |
| Assembly | 11 | |
| Finish | 18 | |
| Paint | 8 | |
| Install | 32 | |
| Travel | 20 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1757.00 | Bar stock | Allied Welding Gas | |
| 1921.00 | Bar stock | Summit Powder Coat | |
| $3678.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 13 | 682.5 | 3 | 157.5 |
| Layout | 13 | 682.5 | 11.7 | 614.25 |
| Assembly | 11 | 577.5 | 0 | |
| Finish | 18 | 945 | 0 | |
| Paint | 8 | 420 | 0 | |
| Install | 32 | 1680 | 0 | |
| Travel | 20 | 1050 | 4 | 210 |
| Total | 115 | $8625.00 | 18.7 | $1402.50 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1546.00 | Tube | Allied Welding Gas | |
| $1546.00 | Total | All Sources | |