21-003 Corvid Coffee Roasters: Spiral Stair
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 17 | |
| Layout | 21 | |
| Assembly | 30 | |
| Finish | 26 | |
| Paint | 16 | |
| Install | 38 | |
| Travel | 13 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 2104.00 | Hardware | Allied Welding Gas | |
| 2092.00 | Bar stock | Keystone Metals Supply | |
| $4196.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 17 | 892.5 | 54.5 | 2861.25 |
| Layout | 21 | 1102.5 | 14.5 | 761.25 |
| Assembly | 30 | 1575 | 15.5 | 813.75 |
| Finish | 26 | 1365 | 4.5 | 236.25 |
| Paint | 16 | 840 | 61 | 3202.5 |
| Install | 38 | 1995 | 11.5 | 603.75 |
| Travel | 13 | 682.5 | 11.5 | 603.75 |
| Total | 161 | $12075.00 | 173 | $12975.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1136.00 | Hardware | Allied Welding Gas | |
| 1509.00 | Powder coat | Summit Powder Coat | |
| $2645.00 | Total | All Sources | |