20-028 Brightwater Commons: Driveway Gate
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Measure & Fit | 25 | |
| Layout | 13 | |
| Assembly | 53 | |
| Finish | 11 | |
| Paint | 7 | |
| Travel | 8 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1240.00 | Powder coat | Allied Welding Gas | |
| $1240.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Measure & Fit | 25 | 1312.5 | 12 | 630 |
| Layout | 13 | 682.5 | 5.5 | 288.75 |
| Assembly | 53 | 2782.5 | 17.5 | 918.75 |
| Finish | 11 | 577.5 | 28 | 1470 |
| Paint | 7 | 367.5 | 31 | 1627.5 |
| Travel | 8 | 420 | 23 | 1207.5 |
| Total | 117 | $8775.00 | 117 | $8775.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 506.00 | Tube | Tri-State Fasteners | |
| $506.00 | Total | All Sources | |