20-024 Pemberton Residence: Pergola
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 7 | |
| Measure & Fit | 16 | |
| Layout | 17 | |
| Assembly | 50 | |
| Finish | 15 | |
| Paint | 11 | |
| Install | 38 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 101.00 | Tube | Keystone Metals Supply | |
| 1603.00 | Plate | Summit Powder Coat | |
| 134.00 | Plate | Allied Welding Gas | |
| $1838.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 7 | 367.5 | 32 | 1680 |
| Measure & Fit | 16 | 840 | 23 | 1207.5 |
| Layout | 17 | 892.5 | 25 | 1312.5 |
| Assembly | 50 | 2625 | 14.4 | 756 |
| Finish | 15 | 787.5 | 13.5 | 708.75 |
| Paint | 11 | 577.5 | 10.5 | 551.25 |
| Install | 38 | 1995 | 13.5 | 708.75 |
| Total | 154 | $11550.00 | 131.9 | $9892.50 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1426.00 | Hardware | Summit Powder Coat | |
| 917.00 | Hardware | Keystone Metals Supply | |
| $2343.00 | Total | All Sources | |