20-020 Vantage Point Hotel: Handrail
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 27 | |
| Measure & Fit | 6 | |
| Layout | 17 | |
| Assembly | 49 | |
| Finish | 4 | |
| Paint | 5 | |
| Install | 51 | |
| Travel | 19 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1757.00 | Powder coat | Tri-State Fasteners | |
| 1871.00 | Plate | Allied Welding Gas | |
| 810.00 | Tube | Summit Powder Coat | |
| $4438.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 27 | 1417.5 | 17.5 | 918.75 |
| Measure & Fit | 6 | 315 | 25.5 | 1338.75 |
| Layout | 17 | 892.5 | 29.5 | 1548.75 |
| Assembly | 49 | 2572.5 | 30.5 | 1601.25 |
| Finish | 4 | 210 | 16.5 | 866.25 |
| Paint | 5 | 262.5 | 20 | 1050 |
| Install | 51 | 2677.5 | 15.5 | 813.75 |
| Travel | 19 | 997.5 | 23 | 1207.5 |
| Total | 178 | $13350.00 | 178 | $13350.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1627.00 | Powder coat | Tri-State Fasteners | |
| $1627.00 | Total | All Sources | |