20-015 Old Mill Lofts: Driveway Gate
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 7 | |
| Measure & Fit | 5 | |
| Layout | 20 | |
| Assembly | 23 | |
| Finish | 9 | |
| Paint | 25 | |
| Travel | 24 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 2316.00 | Tube | Allied Welding Gas | |
| 1831.00 | Plate | Keystone Metals Supply | |
| $4147.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 7 | 367.5 | 14 | 735 |
| Measure & Fit | 5 | 262.5 | 6 | 315 |
| Layout | 20 | 1050 | 17 | 892.5 |
| Assembly | 23 | 1207.5 | 25 | 1312.5 |
| Finish | 9 | 472.5 | 18.5 | 971.25 |
| Paint | 25 | 1312.5 | 13 | 682.5 |
| Travel | 24 | 1260 | 19.5 | 1023.75 |
| Total | 113 | $8475.00 | 113 | $8475.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 132.00 | Hardware | Tri-State Fasteners | |
| $132.00 | Total | All Sources | |