ISME demo: fictional data, read-only. Interversal Systems

20-015 Old Mill Lofts: Driveway Gate

Customer Contact Information

Project Details

Structure

Estimate

Labor Estimate

Type Hours
Handling 7
Measure & Fit 5
Layout 20
Assembly 23
Finish 9
Paint 25
Travel 24

Estimated Cost Sources

Cost Description Vendor
2316.00 Tube Allied Welding Gas
1831.00 Plate Keystone Metals Supply
$4147.00 Total All Sources

REPORT

Labor Summary

Type Estimated Hours Estimated Cost Actual Hours Actual Cost
Handling 7 367.5 14 735
Measure & Fit 5 262.5 6 315
Layout 20 1050 17 892.5
Assembly 23 1207.5 25 1312.5
Finish 9 472.5 18.5 971.25
Paint 25 1312.5 13 682.5
Travel 24 1260 19.5 1023.75
Total 113 $8475.00 113 $8475.00

Costing and Invoices

Cost Description Vendor
132.00 Hardware Tri-State Fasteners
$132.00 Total All Sources

Insights

Billed: $12622.00

Net Profit: $6557.50

Net Profit Margin: 51.952939312312%

Cost Per Foot: $742.47