20-013 Stonefield Township: Handrail
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 20 | |
| Layout | 17 | |
| Assembly | 54 | |
| Paint | 22 | |
| Install | 29 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 2100.00 | Bar stock | Keystone Metals Supply | |
| 1885.00 | Hardware | Keystone Metals Supply | |
| $3985.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 20 | 1050 | 49 | 2572.5 |
| Layout | 17 | 892.5 | 45 | 2362.5 |
| Assembly | 54 | 2835 | 13 | 682.5 |
| Paint | 22 | 1155 | 15 | 787.5 |
| Install | 29 | 1522.5 | 20 | 1050 |
| Total | 142 | $10650.00 | 142 | $10650.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 2386.00 | Powder coat | Summit Powder Coat | |
| 621.00 | Plate | Summit Powder Coat | |
| 662.00 | Plate | Summit Powder Coat | |
| $3669.00 | Total | All Sources | |