20-013 Stonefield Township: Handrail

Customer Contact Information

Project Details

Structure

Estimate

Labor Estimate

Type Hours
Handling 20
Layout 17
Assembly 54
Paint 22
Install 29

Estimated Cost Sources

Cost Description Vendor
2100.00 Bar stock Keystone Metals Supply
1885.00 Hardware Keystone Metals Supply
$3985.00 Total All Sources

REPORT

Labor Summary

Type Estimated Hours Estimated Cost Actual Hours Actual Cost
Handling 20 1050 49 2572.5
Layout 17 892.5 45 2362.5
Assembly 54 2835 13 682.5
Paint 22 1155 15 787.5
Install 29 1522.5 20 1050
Total 142 $10650.00 142 $10650.00

Costing and Invoices

Cost Description Vendor
2386.00 Powder coat Summit Powder Coat
621.00 Plate Summit Powder Coat
662.00 Plate Summit Powder Coat
$3669.00 Total All Sources

Insights

Billed: $14635.00

Net Profit: $3511.00

Net Profit Margin: 23.990433891356%

Cost Per Foot: $inf