20-008 Halvorsen Residence: Driveway Gate
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 9 | |
| Layout | 17 | |
| Assembly | 51 | |
| Finish | 15 | |
| Paint | 8 | |
| Install | 37 | |
| Travel | 7 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1456.00 | Powder coat | Tri-State Fasteners | |
| 120.00 | Tube | Tri-State Fasteners | |
| $1576.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 9 | 472.5 | 31 | 1627.5 |
| Layout | 17 | 892.5 | 12.5 | 656.25 |
| Assembly | 51 | 2677.5 | 30.5 | 1601.25 |
| Finish | 15 | 787.5 | 27.5 | 1443.75 |
| Paint | 8 | 420 | 6 | 315 |
| Install | 37 | 1942.5 | 20 | 1050 |
| Travel | 7 | 367.5 | 16.5 | 866.25 |
| Total | 144 | $10800.00 | 144 | $10800.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 214.00 | Plate | Summit Powder Coat | |
| $214.00 | Total | All Sources | |