20-005 Ridgeline Builders: Fence
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Measure & Fit | 11 | |
| Assembly | 38 | |
| Finish | 18 | |
| Paint | 9 | |
| Travel | 21 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1256.00 | Hardware | Allied Welding Gas | |
| 506.00 | Hardware | Allied Welding Gas | |
| $1762.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Measure & Fit | 11 | 577.5 | 3 | 157.5 |
| Assembly | 38 | 1995 | 28 | 1470 |
| Finish | 18 | 945 | 10.5 | 551.25 |
| Paint | 9 | 472.5 | 19 | 997.5 |
| Travel | 21 | 1102.5 | 36.5 | 1916.25 |
| Total | 97 | $7275.00 | 97 | $7275.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 2130.00 | Plate | Allied Welding Gas | |
| $2130.00 | Total | All Sources | |