19-020 Stonefield Township: Sign Bracket
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Measure & Fit | 23 | |
| Layout | 11 | |
| Assembly | 6 | |
| Finish | 17 | |
| Paint | 12 | |
| Install | 25 | |
| Travel | 17 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1883.00 | Hardware | Summit Powder Coat | |
| 726.00 | Hardware | Summit Powder Coat | |
| $2609.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Measure & Fit | 23 | 1207.5 | 8 | 420 |
| Layout | 11 | 577.5 | 16.1 | 845.25 |
| Assembly | 6 | 315 | 4 | 210 |
| Finish | 17 | 892.5 | 11 | 577.5 |
| Paint | 12 | 630 | 0 | |
| Install | 25 | 1312.5 | 10 | 525 |
| Travel | 17 | 892.5 | 11 | 577.5 |
| Total | 111 | $8325.00 | 60.1 | $4507.50 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1966.00 | Bar stock | Allied Welding Gas | |
| $1966.00 | Total | All Sources | |