19-016 Riverbend Elementary: Spiral Stair

Customer Contact Information

Project Details

Structure

Estimate

Labor Estimate

Type Hours
Handling 14
Measure & Fit 11
Layout 7
Assembly 29
Finish 30
Paint 5
Install 50
Travel 2

Estimated Cost Sources

Cost Description Vendor
2164.00 Tube Tri-State Fasteners
1477.00 Hardware Keystone Metals Supply
$3641.00 Total All Sources

REPORT

Labor Summary

Type Estimated Hours Estimated Cost Actual Hours Actual Cost
Handling 14 735 6 315
Measure & Fit 11 577.5 39.5 2073.75
Layout 7 367.5 19.5 1023.75
Assembly 29 1522.5 7.5 393.75
Finish 30 1575 3.5 183.75
Paint 5 262.5 19 997.5
Install 50 2625 26.5 1391.25
Travel 2 105 26.5 1391.25
Total 148 $11100.00 148 $11100.00

Costing and Invoices

Cost Description Vendor
1860.00 Bar stock Summit Powder Coat
589.00 Powder coat Keystone Metals Supply
531.00 Bar stock Allied Welding Gas
$2980.00 Total All Sources

Insights

Billed: $14741.00

Net Profit: $3991.00

Net Profit Margin: 27.074146937114%

Cost Per Foot: $223.35