19-015 Juniper Row Townhomes: Handrail
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 4 | |
| Measure & Fit | 8 | |
| Finish | 10 | |
| Paint | 6 | |
| Install | 45 | |
| Travel | 27 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1161.00 | Tube | Tri-State Fasteners | |
| 1981.00 | Hardware | Keystone Metals Supply | |
| $3142.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 4 | 210 | 13 | 682.5 |
| Measure & Fit | 8 | 420 | 19 | 997.5 |
| Finish | 10 | 525 | 22 | 1155 |
| Paint | 6 | 315 | 20 | 1050 |
| Install | 45 | 2362.5 | 19 | 997.5 |
| Travel | 27 | 1417.5 | 7 | 367.5 |
| Total | 100 | $7500.00 | 100 | $7500.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1879.00 | Hardware | Summit Powder Coat | |
| $1879.00 | Total | All Sources | |