19-010 Ridgeline Builders: Sign Bracket
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 3 | |
| Measure & Fit | 24 | |
| Layout | 10 | |
| Assembly | 34 | |
| Paint | 18 | |
| Install | 24 | |
| Travel | 25 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 466.00 | Tube | Keystone Metals Supply | |
| $466.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 3 | 157.5 | 26.5 | 1391.25 |
| Measure & Fit | 24 | 1260 | 36 | 1890 |
| Layout | 10 | 525 | 18 | 945 |
| Assembly | 34 | 1785 | 14.5 | 761.25 |
| Paint | 18 | 945 | 19 | 997.5 |
| Install | 24 | 1260 | 6 | 315 |
| Travel | 25 | 1312.5 | 18 | 945 |
| Total | 138 | $10350.00 | 138 | $10350.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1979.00 | Tube | Tri-State Fasteners | |
| $1979.00 | Total | All Sources | |