19-004 Old Mill Lofts: Handrail
Estimate
Labor Estimate
| Type | Hours | |
|---|---|---|
| Handling | 24 | |
| Layout | 5 | |
| Assembly | 44 | |
| Finish | 18 | |
| Paint | 20 | |
| Travel | 9 | |
Estimated Cost Sources
| Cost | Description | Vendor | |
|---|---|---|---|
| 1782.00 | Powder coat | Summit Powder Coat | |
| 230.00 | Hardware | Keystone Metals Supply | |
| $2012.00 | Total | All Sources | |
REPORT
Labor Summary
| Type | Estimated Hours | Estimated Cost | Actual Hours | Actual Cost |
|---|---|---|---|---|
| Handling | 24 | 1260 | 0 | |
| Layout | 5 | 262.5 | 44 | 2310 |
| Assembly | 44 | 2310 | 8 | 420 |
| Finish | 18 | 945 | 23 | 1207.5 |
| Paint | 20 | 1050 | 12 | 630 |
| Travel | 9 | 472.5 | 5 | 262.5 |
| Total | 120 | $9000.00 | 92 | $6900.00 |
Costing and Invoices
| Cost | Description | Vendor | |
|---|---|---|---|
| 1058.00 | Plate | Summit Powder Coat | |
| 813.00 | Hardware | Tri-State Fasteners | |
| $1871.00 | Total | All Sources | |